₹29,340 sq.ft extravaganza
- Rampant plunder in Amaravati construction works: ₹29,340 per square foot!
- Five Secretariat towers: ₹4,242 crore increase in just two revised estimates.
- Glass façade and cladding package: ₹2,540 crore in May, ₹4,830 crore in November.
- Additional ₹2,290 crore in six months, a 90% increase in a single package.
- Main construction estimate increased from ₹4,688.83 crore last year to ₹6,641.21 crore now.
- Another ₹1,952.38 crore added in the name of design modifications, additional steel and fire-resistant paint.
- Total estimated expenditure on the five towers and associated works reaches ₹15,316.94 crore.
- Electrical, air-conditioning, lifts and plumbing works awarded to the same three companies undertaking the main construction.
- Bids substantially exceed departmental estimates in all three tenders.
- How much for each building? How much for each material? How is public money being looted through every contract?
- YSRCP demands that the government answer the people.
The Chandrababu Naidu government continues its unabated plunder through construction works in Amaravati. Estimates are being inflated indiscriminately, facilitating rampant corruption. The entire exercise has been reduced to a policy of looting and accumulating wealth. An estimated expenditure of ₹29,340 per square foot reveals the magnitude of these irregularities.
A glaring example of plunder
On May 1, the Chandrababu government issued a GO stating that glass façade, cladding and associated works for the Amaravati Secretariat towers could be undertaken at a cost of ₹2,540 crore. On November 6, the same government superseded that order and issued another GO increasing the estimate to ₹4,830 crore.
In other words, work estimated to cost ₹100 in May was estimated at ₹190 by November. The additional ₹2,290 crore sanctioned under this single component exceeds the entire original main construction contract value of the five towers awarded in 2018.
What further evidence is needed to demonstrate the plunder taking place in Amaravati under the guise of revised construction estimates?
Additional ₹2,290 crore for glass façades and ₹1,952 crore for main construction
Barely three weeks after nearly doubling the glass façade package, the government increased the main construction expenditure as well.
With the revision approved by the State Cabinet on November 27, the main construction estimate for the five towers increased from ₹4,688.83 crore to ₹6,641.21 crore. A single decision resulted in an additional financial burden of ₹1,952.38 crore, representing an increase of 41.6%.
Design modifications have necessitated additional high-grade structural steel. It has also been proposed to apply fire-resistant paint capable of withstanding fire for two hours to the diagrid steel structure.
The Cabinet has authorised the execution of the revised works through the existing contractors themselves.
Taken together, the revised glass façade package and main construction estimates impose an additional financial burden of ₹4,242.38 crore over their previous estimates.
| Construction component | Earlier estimate (₹ Cr) | Revised estimate (₹ Cr) | Increase (₹ Cr) |
| Main construction | 4,688.83 | 6,641.21 | 1,952.38 |
| Glass façade and cladding | 2,540.00 | 4,830.00 | 2,290.00 |
| Total | 7,228.83 | 11,471.21 | 4,242.38 |
Tenders invited three times, not a single bid received
The revised G.O.Rt.No.1364 states that the original estimate for glass façade works was prepared on the basis of preliminary drawings. Although tenders were invited three times, not a single bid was received.
The government explained that diamond-shaped glass panels require specialised frames, additional aluminium, specialised equipment for installation at considerable heights and the import of six-metre-long stainless steel panels.
This is precisely where the extent of the plunder becomes evident.
Which quantities of work were underestimated before administrative sanction was granted for ₹2,540 crore? What is the financial cost of that error? How much of the subsequent increase is actually attributable to rising material prices?
Only when the government provides a separate financial breakdown of these two components will the facts behind the ₹2,290 crore escalation within six months become clear.
Same towers, same companies, bids above estimates
NCC is the main construction contractor for the GAD Tower, Shapoorji Pallonji for Secretariat Towers 1 and 2, and Larsen & Toubro for Towers 3 and 4.
According to G.O.Rt.Nos.1347, 1348 and 1349, issued on November 2, the bids submitted by the same companies were approved for electrical systems, HVAC, fire protection systems, lifts and plumbing works in their respective towers.
In all three packages, the lowest bid exceeded the departmental estimate. Excluding taxes, the difference between the departmental estimates and the approved bids in these three contracts alone amounts to approximately ₹78.55 crore.
Engineering experts point out that repeatedly awarding the enhanced works to the existing companies is resulting in substantial financial benefits to the contractors.
How did the cost reach ₹29,340 per square foot?
The total built-up area of the five towers is 52,20,496 square feet. Dividing the main construction estimate of ₹6,641.21 crore by this area translates into a cost of ₹12,721 per square foot.
When the expenditure on electrical systems, air-conditioning, lifts and other installations, glass façade and cladding, roads and drainage infrastructure, and architectural designs is added, the cumulative project estimate reaches an astonishing ₹15,316.94 crore.
| S.No. | Construction component | Estimated cost (₹ crore) |
| 1 | Main construction of five Secretariat towers | 6,641.21 |
| 2 | Electrical, HVAC, fire protection, lifts and plumbing | 2,316.88 |
| 3 | Glass façade and cladding works | 4,830.00 |
| 4 | Roads, drainage and other infrastructure | 1,057.62 |
| 5 | Architectural design consultancy | 471.23 |
| Total estimated project cost | 15,316.94 | |
| Total built-up area | 52,20,496 sq. ft. | |
| Average cost per square foot | ₹29,340 |
Of this, the glass façade and cladding package alone accounts for approximately ₹9,252 per square foot of built-up area.
From juice counters in bungalows to the Assembly spire
Under G.O.Rt.No.29, administrative sanction of ₹109.52 crore was granted for home automation, additional wardrobes, juice counters, spiral staircases, covered balconies, additional air-conditioning and electrical systems in the bungalows of senior government officers at Rayapudi.
Even the approved bid for these works exceeded the departmental estimate, as shown in the accompanying table.
G.O.Rt.No.705 specifies an expenditure of ₹547.07 crore for decorative rooftop structures, parking facilities, internal roads, waterbodies and other associated works at the High Court.
Recently, ₹431.79 crore was approved for electrical systems, fire protection, lifts and plumbing works in the High Court.
Similarly, ₹379.82 crore was approved for the Assembly spire, roof, specialised walls and other structural works, ₹353.51 crore for electrical and associated systems, and ₹626.13 crore for the complex comprising the public library, auditorium and Institute of Good Governance.
| Building / Work | Amount (₹ crore) |
| Additional amenities in senior officers’ bungalows at Rayapudi | 109.52 |
| High Court external development and associated works | 547.07 |
| High Court electrical, fire protection, lifts and plumbing works | 431.79 |
| Assembly spire, roof, specialised walls and structural works | 379.82 |
| Assembly electrical and associated systems | 353.51 |
| Public Library, Auditorium and Institute of Good Governance complex | 626.13 |
Why have the estimates nearly doubled?
The question is not how many floors the towers have. The Chandrababu government must explain to the people why the estimate prepared for glass façade works in May nearly doubled by November.
How did an additional ₹1,952 crore worth of works emerge this year in the main construction estimate finalised last year?
The government must disclose a comparative statement of the original and revised estimates, specifying the quantities of steel in tonnes, glass panels in square metres, and the earlier and revised rates for each unit.
Analysts point out that despite the extensive evidence of plunder in the construction of the five towers, the government’s failure to provide answers is indicative of corruption.
How much has the cost increased for each tower?
Details of the main construction contracts awarded in 2018 and 2025.
All amounts in ₹ crore.
| Building | Main construction contract, 2018 | Contract value in 2025, including taxes and other charges | Increase | Revised glass façade and cladding allocation |
| Secretariat Towers 1 and 2 | 932.46 | 1,762.81 | 830.35 | 1,945.20 |
| Secretariat Towers 3 and 4 | 784.62 | 1,545.55 | 760.93 | 1,790.20 |
| Chief Minister’s Office and GAD Tower | 554.06 | 1,046.07 | 492.01 | 1,094.60 |
A comparison of the original and revised contracts reveals that Secretariat Towers 1 and 2 recorded the highest increase of ₹830.35 crore. These two towers also account for the largest allocation under the revised glass façade package.
The latest increase of ₹1,952.38 crore in main construction expenditure is a combined amount covering all five towers.
Bids exceeding departmental estimates in other buildings as well
| Building / Work | Departmental estimate (₹ Cr) | Approved bid (₹ Cr) | Excess (₹ Cr) | Excess (%) | GO No. |
| Quantum Valley twin office towers: Main construction | 958.40 | 1,002.49 | 44.09 | 4.60% | 1009 |
| Secretariat Towers 1 and 2: Electrical, lifts and associated works | 737.76 | 768.90 | 31.13 | 4.22% | 1348 |
| Secretariat Towers 3 and 4: Electrical, lifts and associated works | 679.19 | 708.13 | 28.93 | 4.26% | 1349 |
| GAD Tower: Electrical, lifts and associated works | 429.83 | 448.32 | 18.48 | 4.30% | 1347 |
| Governor’s residential complex (Lok Bhavan) | 162.40 | 169.92 | 7.52 | 4.63% | 1470 |
| Andhra Pradesh Judicial Academy | 125.50 | 130.38 | 4.88 | 3.89% | 778 |
| Additional works in All India Services officers’ bungalows at Rayapudi | 90.48 | 94.91 | 4.42 | 4.89% | 704 |
| Amaravati Quantum Computing Centre | 99.62 | 103.96 | 4.34 | 4.36% | 21 |
The differences have been calculated using the exact rupee values specified in the respective Government Orders and expressed in crores.
Quantum Valley Twin Towers | G.O.Rt.No.1009
The departmental estimate for the main construction of twin office towers in Amaravati Quantum Valley was ₹958.40 crore.
The government approved the bid of ₹1,002.49 crore submitted by Larsen & Toubro, which is ₹44.09 crore (4.60%) above the departmental estimate.
Secretariat Towers 1 and 2 | G.O.Rt.No.1348
The departmental estimate for electrical systems, air-conditioning, fire protection, lifts and plumbing works in Secretariat Towers 1 and 2 was ₹737.76 crore.
The government approved the bid of ₹768.90 crore submitted by Shapoorji Pallonji, which is ₹31.13 crore (4.22%) above the departmental estimate.
Secretariat Towers 3 and 4 | G.O.Rt.No.1349
The departmental estimate for electrical systems, air-conditioning, fire protection, lifts and plumbing works in Secretariat Towers 3 and 4 was ₹679.19 crore.
The government approved the bid of ₹708.13 crore submitted by Larsen & Toubro, which is ₹28.93 crore (4.26%) above the departmental estimate.
GAD Tower | G.O.Rt.No.1347
The departmental estimate for electrical systems, air-conditioning, lifts, fire protection and plumbing works in the General Administration Department (GAD) Tower of the Secretariat was ₹429.83 crore.
The government approved the bid of ₹448.32 crore submitted by NCC, which is ₹18.48 crore (4.30%) above the departmental estimate.
Governor’s Residential Complex (Lok Bhavan) | G.O.Rt.No.1470
The departmental estimate for the construction of the Lok Bhavan complex in Amaravati, comprising the Governor’s residence, office and Durbar Hall, was ₹162.40 crore.
The government approved the bid of ₹169.92 crore submitted by BSR Infratech India, which is ₹7.52 crore (4.63%) above the departmental estimate.
Andhra Pradesh Judicial Academy | G.O.Rt.No.778
The departmental estimate for the construction of the Andhra Pradesh Judicial Academy at Pitchikalapalem in the Amaravati capital region was ₹125.50 crore.
The government approved the bid of ₹130.38 crore submitted by NCC, which is ₹4.88 crore (3.89%) above the departmental estimate.
Senior Government Officers’ Bungalows at Rayapudi | G.O.Rt.No.704
The departmental estimate for additional works in the bungalows of All India Services officers at Rayapudi, including home automation, juice counters and spiral staircases, was ₹90.48 crore.
The government approved the bid of ₹94.91 crore submitted by KMV Projects, which is ₹4.42 crore (4.89%) above the departmental estimate.
Amaravati Quantum Computing Centre | G.O.Rt.No.21
The approved project estimate for the design and construction of the Amaravati Quantum Computing Centre was ₹99.62 crore.
The government approved the bid of ₹103.96 crore submitted by Larsen & Toubro, which is ₹4.34 crore (4.36%) above the departmental estimate.